How many days does a claimant have from project completion to file a written notice to hold and claim a lien with the county recorder?

  1. 30 days

  2. 60 days

  3. 90 days

  4. 120 days

The correct answer is: 90 days

The correct answer highlights a key aspect of the lien process in construction law. In Utah, a claimant, which often includes contractors, subcontractors, or suppliers, is required to file a written notice to hold and claim a lien within 90 days following the completion of the project. This notice is crucial as it serves to inform the property owner and other interested parties about the intent to file a lien against the property due to non-payment or disputes regarding the work done or materials supplied. Understanding this timeline is vital for anyone involved in construction projects as it ensures that they protect their right to claim payment through a lien if necessary. Missing the 90-day window could result in losing the right to claim a lien altogether, which could lead to significant financial loss for the claimant. The other options represent timeframes that do not align with Utah's statutory requirements for lien claims. Familiarity with these timelines aids in ensuring compliance with local laws and protects the interests of those providing labor or materials in the construction industry.